Lost Productivity Damages in Construction: The Modified Total Cost Method

By John Mark Goodman on December 26, 2024
Email this postTweet this postLike this postShare this post on LinkedIn
Lost Productivity Damages in Construction: The Modified Total Cost Method

Here at Bradley we frequently represent clients pursuing or opposing claims for lost productivity on construction jobs. The gist of those claims is that something happened which decreased productivity and thereby increased costs. That something can be just about anything.  Differing site conditions. Unreasonable or conflicting instructions. A global pandemic. Lost productivity claims seek to reallocate costs from the party who incurred them to the party who caused them or otherwise bears that risk under the contract. While identifying the cause of lost productivity can be relatively straightforward, quantifying its impact can be tricky and often requires expert testimony. A Montana federal court recently addressed expert testimony requirements for quantifying a lost productivity claim in Exxon Mobil Corporation v. AECOM Energy, 2024 WL 5137523 (D. Montana, Dec. 17, 2024).

That case involves a dispute over turnaround work that the contractor was hired to do at an oil refinery in Billings, Montana. The turnaround took 17 weeks instead of seven. Litigation ensued with both sides seeking to recover cost from the other. The contractor seeks $33M in lost productivity costs allegedly caused by the owner’s failure to plan and prepare for the work and the unexpected deterioration of certain equipment at the refinery. In support of that claim, the contractor has offered the opinion of two experts witnesses who rely upon the Modified Total Cost Method of computing lost productivity damages. We previously wrote about that method here. Here is how the court described that method and its relation to the unmodified Total Cost Method:

The total cost method is based on a formula that assumes that a contractor is owed the difference between the actual cost of the contract and the contractor’s bid. Under the total cost method, a contractor must prove: (1) the impracticability of proving its actual losses directly; (2) the reasonableness of its bid; (3) the reasonableness of its actual costs; and (4) lack of responsibility for the added costs. This method has always been viewed with disfavor, in part because of concerns about bidding inaccuracies, which can reduce the contractor’s estimated costs, and performance inefficiencies, resulting in inflated expenditures. The modified total-cost method addresses some of the objections to the total cost method by adjusting it for a contractor’s lack of proof as required in the total cost method.

In examining claims  based on a total cost or a modified total-cost methodology, courts require safeguards to ensure, to the extent possible, that the burden of excess expenditures falls on the party responsible for them. Under a modified total-cost approach, a contractor still has the burden of proving the four elements required for the total cost method, but the burden is not as stringent. The total cost method [is] used as ‘only a starting point’ with such adjustments thereafter made in such computations as allowances for various factors as to convince the court that the ultimate, reduced figure fairly represents the increased costs the contractor directly suffered from the particular action of defendant which was the subject of the complaint.

The owner moved to exclude the contractor’s damage experts claiming they had not satisfied prongs 2 (reasonableness of bid) and 3 (reasonableness of cost). As to prong 2, the experts leaned heavily on the owner’s internal analyses showing that the contractor’s bid compared favorably with other bidders and with the owner’s own estimates. The expert had also consulted with the contractor’s estimator team to better understand the basis of the bid. As to prong 3, the experts had made a number of adjustments to the contractor’s actual costs in an effort to carve out costs for which the owner was not responsible. For example, they subtracted hours submitted as cost-reimbursable, removed hours for workers who did not perform more than 72 hours of direct labor, and reduced the total hours by 1.5% to account for alleged deficiencies in weld quality.

In denying the owner’s motion, the court found that the experts satisfied both disputed prongs of the modified total cost method and therefore offered reliable expert opinions under Federal Rule of Evidence 702.   The court determined exclusion was unnecessary, and any challenges to the experts’ opinions could be explored by the owner on cross-examination at trial, which is set to begin next month. 

A copy of the court’s opinion can be found here.

Photo of John Mark Goodman John Mark Goodman

John Mark Goodman has been with Bradley his entire legal career as a member of Bradley’s Litigation and Construction practice groups. He has an engineering degree from Georgia Tech and a law degree from Virginia. John Mark has had the privilege of representing…

John Mark Goodman has been with Bradley his entire legal career as a member of Bradley’s Litigation and Construction practice groups. He has an engineering degree from Georgia Tech and a law degree from Virginia. John Mark has had the privilege of representing clients throughout the U.S. and abroad in a wide variety of litigation and arbitration matters, including construction disputes, products liability claims, tax appeals, breach of contract/warranty, patent disputes, trade secret theft, and general commercial litigation.

Read more about John Mark GoodmanEmail
Show more Show less
  • Posted in:
    Real Estate & Construction
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

LexBlog, Inc. logo
Facebook LinkedIn Twitter RSS
Real Lawyers
99 Park Row
  • About LexBlog
  • Careers
  • Press
  • Contact LexBlog
  • Privacy Policy
  • Editorial Policy
  • Disclaimer
  • Terms of Service
  • RSS Terms of Service
  • Products
  • Blog Pro
  • Blog Plus
  • Blog Premier
  • Microsite
  • Syndication Portals
  • LexBlog Community
  • Resource Center
  • 1-800-913-0988
  • Submit a Request
  • Support Center
  • System Status
  • Resource Center
  • Blogging 101

New to the Network

  • Beyond the First 100 Days
  • In the Legal Interest
  • Cooking with SALT
  • The Fiduciary Litigator
  • CCN Mexico Report™
Copyright © 2025, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo