Method of Calculating Recovery Of Extended Home Office Overhead

By Joseph Hackenbracht on October 30, 2007
Email this postTweet this postLike this postShare this post on LinkedIn

In a decision earlier this month, the Armed Services Board of Contract Appeals reiterated that the recovery of unabsorbed home office overhead, based on the Eichleay formula, is for “a stand-by of an uncertain duration.” The Board held that where a contractor is entitled to a compensable contract time extension for additional work, the contractor is entitled to recover extended home office overhead.  Extended home office overhead is calculated as a fixed percentage markup of costs incurred during the contract time extension. Fru-Con construction Corporation, ASBCA No. 55197, 55248, October 4, 2007. For a discussion on the Eichleay formula and the recovery of unabsorbed home office overhead, see our earlier article.

Photo of Joseph Hackenbracht Joseph Hackenbracht

Joseph A. Hackenbracht is a Partner in the Federal Contracting Group of Cohen Seglias Pallas Greenhall & Furman and practices in all phases of federal government contract and construction law. He is often called upon to advise clients concerning contract interpretation and to…

Joseph A. Hackenbracht is a Partner in the Federal Contracting Group of Cohen Seglias Pallas Greenhall & Furman and practices in all phases of federal government contract and construction law. He is often called upon to advise clients concerning contract interpretation and to assist clients in the preparation of proposals for negotiated procurements. Joseph has extensive experience handling protests, contract claims, appeals to administrative boards of contract appeals, and litigation in various Federal courts. He has prepared and litigated claims involving the many issues which arise concerning construction, including defective design, defective specifications, differing site conditions, changes, suspensions, delays and contract terminations.

Read more about Joseph HackenbrachtEmailJoseph's Twitter Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Federal Construction Contracting Blog
  • Organization:
    Cohen Seglias Pallas Greenhall & Furman
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo