Terminology Differences Between a "Bidder" and an "Offeror"

By Michael H. Payne on June 27, 2011
Email this postTweet this postLike this postShare this post on LinkedIn

By: Michael H. Payne

Government contractors frequently use incorrect terminology to describe a solicitation. For example, clients often call me and ask why they were not awarded a contract even though they had submitted the lowest bid. The first thing that I ask is whether the solicitation was a Request for Proposals (“RFP”), or an Invitation for Bid (“IFB”). If it was an RFP, the award was probably based on best value and the lowest-priced proposal would not necessarily receive the award. If the solicitation was an IFB, there would be more of a question about why an award was not made to the lowest-priced bidder. Of course, even in sealed bidding the lowest bidder must also be responsive and responsible in order to receive an award, so there can be a valid reason as to why the lowest bidder did not receive the award.

The best way to show that you understand the basics of the federal procurement process is to remember that responses to an IFB (sealed bid solicitation) are referred to as “bids,” and responses to an RFP (negotiated procurement) are referred to as “proposals” or “offers.” In other words, the proper terms under an IFB are “bid,” “bidder,” and “sealed bid,” and the proper terms under an RFP are “proposal,” “offer,” and “offeror.” Your lawyer will become very confused if you mix these terms by saying, for example, “I just submitted a bid on an RFP.” Sometimes, the only way that I can figure out what my client is talking about is to ask for the solicitation number (the “R” or the “B” in the middle will be a dead giveaway), or I may simply ask my client to send me a copy of the solicitation.

Of course, government procurement personnel frequently add to the confusion. RPPs are often referred to as “negotiated procurements” even though there usually are no negotiations (or “discussions”), and contracting officers often refer to both bids and proposals as “bids,” To make matters worse, the GAO and the courts refer to protests of either an IFB or an RFP as “bid protests.” No wonder there is so much confusion.

Michael H. Payne is the Chairman of the firm’s Federal Practice Group and, together with other experienced members of the group, frequently advises contractors on federal contracting matters, including teaming arrangements, negotiated procurements, bid protests, claims, and appeals.

Photo of Michael H. Payne Michael H. Payne

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of…

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of contract claims and the litigation of appeals. Michael has vast experience in federal government contracting, stemming from his time as Chief Trial Attorney for the North Atlantic Division of the Army Corps of Engineers, and is recognized in the federal construction contracting industry as an attorney who enjoys a good working relationship with government agencies.

Continue Reading

Read more about Michael H. PayneEmailMichael's Linkedin ProfileMichael's Twitter Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Federal Construction Contracting Blog
  • Organization:
    Cohen Seglias Pallas Greenhall & Furman
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo