Interconnection customers:  be on notice.  Your interconnection agreement may not be just a transmission provider service agreement that allows your project to interconnect with the transmission system.  It may also be a rate schedule–your rate schedule–that you must file with FERC or suffer the consequences for violating the Federal Power Act.  

 

At last week’s open meeting, FERC issued a decision in Chehalis Power Generating, LP where FERC recapped the longstanding requirement that public utilities must file the rates, terms, and conditions for the jurisdictional services they provide.  So far, so good.  But the Chehalis decision focuses on an interconnection customer who, for some time, provided uncompensated reactive power service under its interconnection agreement–a service that is provided by all interconnection customers who are required to operate their projects within a specified power factor range.  (If you’re keeping track, that’s everyone but wind projects.)  In fact, FERC’s pro forma interconnection agreement even requires interconnection customers to operate their projects in this way in order to maintain reliability.  

 In Chehalis, FERC said the following:  “In order to clarify the Commission’s policy related to reactive power service provided without compensation, the Commission finds that, on a prospective basis, for any jurisdictional reactive power service (including within dead-the-deadband reactive power service [i.e., the service that nearly all interconnection customers supply]) provided by both existing and new generators, the rates, terms, and conditions for such service must be pursuant to a rate schedule on file with the Commission, even though the rate schedule would provide no compensation for such service.”  (brackets added)

In other words, interconnection customers who have not offered to provide any service but who instead operate their projects pursuant to the requirements that have been imposed by FERC, and who do so without compensation, must file their interconnection agreements as a rate schedule. But what regulatory purpose does this serve?    

As a result of the Chehalis decision, FERC will be holding a workshop to explore the mechanics of filing reactive power rate schedules for which there is no compensation.  At a minimum, I hope that FERC exempts all interconnection customers who provide uncompensated reactive power services from any filing requirement.  If not, FERC Staff will be very busy.

 

 

Photo of Jason Johns Jason Johns

Jason Johns advises independent power producers, utilities, investors, and large users of gas and power resources with matters arising in power markets and state and federal energy regulatory arenas. Jason appears regularly in proceedings before the Federal Energy Regulatory Commission and in negotiations…

Jason Johns advises independent power producers, utilities, investors, and large users of gas and power resources with matters arising in power markets and state and federal energy regulatory arenas. Jason appears regularly in proceedings before the Federal Energy Regulatory Commission and in negotiations at the ISO/RTO level, where he represents independent power developers and utilities. His experience includes negotiating major facility contracts, such as interconnection, transmission, and power purchase agreements; prosecuting disputes at FERC; and counseling and defending clients on issues related to regulatory compliance.

Jason also works closely with large commercial and industrial users of electricity and gas, such as aerospace companies, pulp and paper mills, steel mills, and tech company data centers. In that role, Jason helps clients negotiate power and gas supply contracts, interstate pipeline capacity asset management agreements, and pipeline bypass agreements. Jason has also assisted these clients with demand management agreements, the installation of on-site resources (such as battery storage, fuel cells, and solar PV), and with retail and wholesale power purchase agreements for renewable energy and other resources. Jason also serves as a board member of The Climate Trust, a national leader in carbon offset projects and innovative climate change solutions.

Jason and his wife are parents to two growing boys, and they live just outside of Portland, Oregon.

Click here for Jason John’s full bio.