ASBCA Finds Hesitation Is Not Repudiation

By Michelle E. Litteken on November 4, 2014
Email this postTweet this postLike this postShare this post on LinkedIn

When the Government terminates a contract for default (“T for D”), there can be a series of nasty consequences for contractors. Among other things, the contractor may be liable for actual or liquidated damages and for excess costs of reprocurement or completion; the contractor can be suspended or debarred; and the Government is not liable for the costs of unaccepted work and is entitled to the return of progress, partial, or advance payments. In contrast, when a contract is terminated for convenience (“T for C”), the contractor is usually entitled to the costs of goods and services furnished, demobilization costs, and a reasonable profit on the work performed. Also, because a T for C is not a breach, neither party is liable for lost profits or other damages allowed for breach of contract.

Default, directional sign

Suffice it to say, a contractor has a big incentive to fight a T for D—and try to have it converted to a T for C (which is the remedy if a T for D is not justified under the circumstances). Recently, the ASBCA issued parallel decisions denying the Government’s motions for summary judgment in a contractor’s challenges to T for Ds, finding in both cases that the Government had not established a prima facie case that the termination was justified. The Board’s opinions in the Capy Machine Shop, Inc. cases may prove useful to contractors challenging a default termination.

The facts in the two decisions are similar. On two occasions, the Capy Machine Shop accepted an order for aircraft parts. Both orders incorporated FAR 52.249-8 Default (Fixed-Price Supply and Service). Several months later, but before the delivery dates, the contractor asked the contracting officer to cancel the contracts at no cost because “Capy’s forming vendor cannot locate his tooling.” In response, the contracting officer issued show cause notices and advised Capy that it was considering terminating the contracts for default. The contracting officer wrote:

Pending a final decision in this matter, it will be necessary to determine whether your failure to perform arose from causes beyond your control and without your fault or negligence. Accordingly, you are given the opportunity to present, in writing, any facts bearing on the question to me . . . within 10 days after receipt of this notice . . ..

In response, Capy’s general manager explained that the cost of new tooling for one contract was $19,647 and $26,512 for the other, and those costs were not included in either quote. The agency terminated the contracts for default, and Capy appealed the decisions to the Board. In its appeal, Capy noted that the ordered parts required tooling, and when Capy provided its quote, it believed the tooling was available. After award, Capy discovered that the tooling could not be located, and it would have to create new tooling—which it could not afford.

At the Board, the Government moved for summary judgment. The Board denied that motion, finding that the Government had not demonstrated that Capy repudiated the contract. The Board pointed out that Capy contacted the agency twice about each order—once to request a no-cost cancellation, and once to explain that the cost of new tooling was not included in its quote. At no point did the communications “reflect a positive, definitive, unconditional and unequivocal refusal to perform”—as required for anticipatory repudiation.

Although the recent decisions did not resolve Capy’s claims, they are important victories for the contractor. If the Board ultimately finds that the termination was not justified, the contractor will not be liable for damages, reprocurement costs, or completion costs. The Capy Machine Shop, Inc. decisions are useful precedent to cite when challenging a termination for convenience if the contractor has not expressly repudiated performance.

Photo of Michelle E. Litteken Michelle E. Litteken

Michelle Litteken is a Litigation & Dispute Resolution associate in Mayer Brown’s Washington DC office. Michelle’s practice focuses on government contracts matters. She represents clients regarding federal procurement practices and activities, such as litigating large contract disputes and bid protests before the United…

Michelle Litteken is a Litigation & Dispute Resolution associate in Mayer Brown’s Washington DC office. Michelle’s practice focuses on government contracts matters. She represents clients regarding federal procurement practices and activities, such as litigating large contract disputes and bid protests before the United States Court of Federal Claims and the Government Accountability Office. She also provides advice for transactions that implicate government contracts, such as acquisitions of domestic companies that hold government contracts by foreign corporations. Michelle has experience with other areas of litigation, including class actions, federal antitrust claims, federal securities claims, and commercial contract claims.

Read Michelle’s full bio.

Email
Show more Show less
  • Posted in:
    Business and Commercial
  • Blog:
    Meaningful Discussions
  • Organization:
    Mayer Brown
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo