Tricks of the Protest Trade: A Required “Explanation” Does Not Toll GAO’s Limitations Period—As a Mandatory “Debriefing” Does

By Luke Levasseur & Polly A. Myers on June 2, 2015
Email this postTweet this postLike this postShare this post on LinkedIn

Yet another unwary government contractor has been turned away by GAO because it failed to file its protest on time. Unsuccessful offerors that contest evaluation issues (rather than solicitation defects) have 10 days to file protests at GAO. That generally applicable 10-day deadline is tolled when a “debriefing” is required in FAR Part 15 (and certain Part 16) procurements. But that tolling rule doesn’t apply when the FAR only requires that the agency provide an “explanation” to disappointed offerors (e.g., in FAR Parts 8, 12, and 13 procurements)—and does not mandate a “debriefing.” GAO’s decision in Gorod Shtor illustrates this rule by dismissing the protest of an offeror that fell into this bid protest trap.

Gorod ShtorGorod Shtor wanted to sell drapery making and installation services for the U.S. embassy in Moscow. Gorod Shtor submitted a proposal for an IDIQ contract with the Department of State. Importantly, the RFQ was issued as a commercial item acquisition (under FAR Part 12) in which simplified acquisition procedures were applied under FAR Subpart 13.5. Award was to be made on a lowest-priced, technically acceptable basis.

The Agency’s award notice informed the disappointed offeror that the contract was awarded to a competitor, which Gorod Shtor believed did not meet certain RFQ requirements. The notice also stated “[i]f you desire a debriefing, please refer to FAR [] 52.212-1(l)” which lists the types of information to be provided by a debriefing but does not create a right to a debriefing. Gorod Shtor requested a debriefing and was informed of “the reasons why the agency had found the vendor to be technically unacceptable.”

The statutory requirements applicable to GAO bid protests impose a jurisdictional 10-day deadline that runs from the date when “the basis of protest is known or should have been known (whichever is earlier).” That generally applicable limitations period is tolled by GAO’s protest regulation, 4 C.F.R. § 21.2(a)(2)—but only for challenges to awards in which “a debriefing is requested and, when requested, is required.” Such awards occur under FAR Part 15 (and with respect to certain awards under FAR Part 16).

Although the agency’s and Gorod Shtor’s communications talked in terms of a “debriefing,” the relevant part of FAR Part 13 does not mandate a “debriefing.” Instead, the FAR says that “[i]f a supplier requests information on an award that was based on factors other than price alone, a brief explanation of the basis for the contract award decision shall be provided.” The distinction between the “brief explanation” to be provided under FAR Part 13 and a “debriefing” required under FAR Part 15 creates a trap into which Godor Shtor’s protest fell.

As GAO explained, the “brief explanation of the basis for the contract award” required by FAR Part 13 does not toll the limitations period in the same way that a mandatory debriefing does. (Notably, similar “explanations” are provided under FAR Parts 8 and 12.) As such, Gorod Shtor’s receipt of a “debriefing” that the agency was not required to provide did not toll the 10-day statute of limitations—which ran from the date of the award notice. The fact that the agency provided a “debriefing” to Gorod Shtor was surely confusing to the disappointed offeror relative to the running of the limitations period—but it could not expand GAO’s statutory and regulatory requirements that barred the protest.

One can reasonably question whether the regulations should mandate debriefings for more procurements—as good debriefings reduce protest risk (albeit with increased burdens on an agency). But under the current regulations, GAO’s decision correctly reveals a trap for the potential protester in FAR Part 8, 12, 13, and some Part 16 procurements.

Photo of Luke Levasseur Luke Levasseur

Luke Levasseur’s litigation practice focuses on government contract matters. He advises and represents clients regarding federal procurement practices and activities. For the past several years, Luke’s practice has focused on litigating large contract disputes and bid protests before the US Court of Federal…

Luke Levasseur’s litigation practice focuses on government contract matters. He advises and represents clients regarding federal procurement practices and activities. For the past several years, Luke’s practice has focused on litigating large contract disputes and bid protests before the US Court of Federal Claims and the Government Accountability Office. He has also represented clients and performed substantial work with respect to False Claims Act litigation. Luke also has experience handling a variety of other federal court litigation for clients, involving such matters as antitrust claims, a trademark dispute and alleged fraud.

Read Luke’s full bio.

Read more about Luke LevasseurEmail
Show more Show less
Photo of Polly A. Myers Polly A. Myers

Polly A. Myers is a staff attorney in the Litigation & Dispute Resolution practice, where her practice focuses primarily on government contracts including litigation of bid protests before the US Court of Federal Claims and the Government Accountability Office. She has also represented…

Polly A. Myers is a staff attorney in the Litigation & Dispute Resolution practice, where her practice focuses primarily on government contracts including litigation of bid protests before the US Court of Federal Claims and the Government Accountability Office. She has also represented clients in False Claims Act litigation, Small Business Size Determinations, and issues involving Multiple Award Schedule issues, and advised clients in requests and defense of Freedom of Information Act requests.

Read Polly’s full bio.

Read more about Polly A. MyersEmail
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Meaningful Discussions
  • Organization:
    Mayer Brown
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo