Defenses to a Termination for Default

By Michael H. Payne on November 30, 2015
Email this postTweet this postLike this postShare this post on LinkedIn

In a post publisConstruction Sitehed in 2013, we addressed the use of termination for default as a weapon. Unfortunately, construction contractors who fall behind schedule are automatically on the defensive and they rarely find that contracting officers are willing to concede government responsibility. The government, of course, is in a difficult position when it must explain to its customer – the end-user – that the scheduled completion date will not be met. All too often, instead of admitting that the contractor is not responsible, the threat of a termination for default is held over the contractor’s head because it is easier to blame the contractor than to admit that the government made a mistake.

The standard FAR “Default” clause (FAR 52.249-14) provides that a delay is excusable and does not provide a valid basis to terminate the contract for default if it is “beyond the control and without the fault or negligence” of the contractor. For a delay to be excusable under a construction contract, it must also be “unforeseeable.” A contractor may be excused if the delay is caused by defective government specifications, differing site conditions, constructive changes, a waiver of the contract completion date, or a failure of the government to comply with the procedural requirements that must be followed to support a termination for default. It is important for a contractor to document government-caused delays as they occur, rather than waiting to build a case after the fact.

The cases have held that a default termination is a drastic action that must not be undertaken without good cause. The FAR (49.402-3(f)) lists the factors that a CO “shall consider” in determining whether to terminate a contract for default:

  1. The terms of the contract and applicable laws and regulations.
  2. The specific failure of the contractor and the excuses for the failure.
  3. The availability of the supplies or services from other sources.
  4. The urgency of the need for the supplies or services and the period of time required to obtain them from other sources, as compared with the time delivery could be obtained from the delinquent contractor.
  5. The degree of essentiality of the contractor in the Government acquisition program and the effect of a termination for default upon the contractor’s capability as a supplier under other contracts.
  6. The effect of a termination for default on the ability of the contractor to liquidate guaranteed loans, progress payments, or advance payments.
  7. Any other pertinent facts and circumstances.

If a contractor has abandoned performance, or has clearly demonstrated an inability to complete the project in a timely manner, the decision to terminate is easy and difficult to oppose. In many cases, however, there are excusable causes of delay and it is not uncommon for defective specifications to be the culprit. Although FAR 52–233–1(i), requires a contractor to “proceed diligently with performance” while a dispute awaits resolution, there may be extenuating circumstances. For example, the Court of Federal Claims has stated that a contractor may be excused when the Government fails to provide reasonable clarification of a contract’s scope of work upon request. It has also been held that a contractor is not always obligated to continue performance if the decision to stop work is warranted by the particular facts.

We are not suggesting that a contractor should feel free to stop performance because it believes there is an excusable cause of delay. That is a dangerous strategy and should always be discussed with legal counsel. Let’s face it, it is difficult for a contractor to defend its position after it has been terminated. The interim financial hardship and impact to its performance rating is too severe. It is important, however, for a contractor to thoroughly document what has occurred and to continuously inform the government about why the delays are not its fault. A delay analysis that shows the impact of events to the critical path, with an emphasis on government-caused impacts, can be very useful. In the end, be courteous, vocal, persuasive, engaged, and never be silent.

Michael H. Payne is the Chairman of the firm’s Federal Contracting Practice Group and, together with other experienced members of the group, frequently advises contractors on federal contracting matters including bid protests, claims and appeals, procurement issues, small business issues, and dispute resolution.

Photo of Michael H. Payne Michael H. Payne

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of…

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of contract claims and the litigation of appeals. Michael has vast experience in federal government contracting, stemming from his time as Chief Trial Attorney for the North Atlantic Division of the Army Corps of Engineers, and is recognized in the federal construction contracting industry as an attorney who enjoys a good working relationship with government agencies.

Continue Reading

Read more about Michael H. PayneEmailMichael's Linkedin ProfileMichael's Twitter Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Federal Construction Contracting Blog
  • Organization:
    Cohen Seglias Pallas Greenhall & Furman
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo