Timely Documentation is Critical

By Michael H. Payne on January 6, 2016
Email this postTweet this postLike this postShare this post on LinkedIn

In a recent decision by the Armed Services Board of Contract Appeals, Dick Pacific Construction Co., Ltd., ASBCA No. 57675 et. al., decided on December 15, 2015, the Board repeated something that has been said many times before:

We consider daily logs to be the most reliable evidence of what actually happened during construction. Technocratica, ASBCA No. 46567 et al., 99-2 BCA ¶ 30,391 (“Daily inspection reports have been held to be prima facie evidence of the daily conditions as they existed at the time of performance.”)

Boards and courts often refer to daily reports as “contemporaneous records,” because they were created at the time that the events occurred and usually well before a claim was anticipated.  It is for that reason that such records are assigned greater credibility than documents created after the fact.Inspector at construction ares

Field personnel on a construction project have many important things to do in a given day, but they are well advised to take the time to record specific events that may have an impact on the time or cost of performance.  The “remarks” section on a daily report is particularly important.  If a Quality Control Representative is asked to testify about conditions on the site that occurred several years earlier, the memory of the witness will be much more believable if his recollections are supported by contemporaneous records.

Michael H. Payne is the Chairman of the firm’s Federal Contracting Practice Group and, together with other experienced members of the group, frequently advises contractors on federal contracting matters including bid protests, claims and appeals, procurement issues, small business issues, and dispute resolution.

Photo of Michael H. Payne Michael H. Payne

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of…

As Chair of the firm’s growing Government Contracting Group, Michael represents contractors, subcontractors, and suppliers on a wide range of federal contracting issues, including the interpretation of solicitation and contract provisions, the filing of bid protests, resolution of disputes, and the preparation of contract claims and the litigation of appeals. Michael has vast experience in federal government contracting, stemming from his time as Chief Trial Attorney for the North Atlantic Division of the Army Corps of Engineers, and is recognized in the federal construction contracting industry as an attorney who enjoys a good working relationship with government agencies.

Continue Reading

Read more about Michael H. PayneEmailMichael's Linkedin ProfileMichael's Twitter Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Federal Construction Contracting Blog
  • Organization:
    Cohen Seglias Pallas Greenhall & Furman
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo