Miller Time: Where to File a Miller Act Suit Arising on an Overseas Project?

Subcontractors filing Miller Act lawsuits in the U.S. must generally do so in the federal district court where the contract from which the dispute arose was “performed and executed.” 40 USC  §§ 3131-3134  However, on contracts performed outside of the U.S., the court that is the proper venue for a Miller Act lawsuit can be a murky issue. This is, perhaps, one of the reasons why the Miller Act permits a contracting officer to waive the Act’s payment and performance bond requirements on work performed abroad if it is found “impracticable for the contractor to furnish such bonds.” Federal courts have also held that parties may waive the Miller Act venue requirement through a valid forum selection clause in a contract agreement.

Where the contracting officer does not waive the Miller Act requirements and the parties do not agree on a forum selection clause for a contract performed abroad, all federal district courts may have jurisdiction over a Miller Act claim filed by a subcontractor under the federal contract at issue. Determining proper venue in these circumstances requires a more complicated factual analysis of the dispute.

In the past, courts have considered factors such as where the parties executed the contract, where supplies or services were to be delivered, and the site of performance in evaluating whether a “sufficient nexus” existed to satisfy the Miller Act venue requirement.  Since the latter two factors would not apply to an overseas project, courts may consider where the contract was executed as a decisive factor in determining venue for a Miller Act suit on the U.S. federal supply or services contract to be performed abroad, but this issue has not been conclusively resolved. By addressing venue concerns during contract negotiations with subcontractors or in discussions with the government, federal contractors may be able to avoid placing the venue determination in the hands of a judge, where the result may be unpredictable and unfavorable.

Click here to view as PDF

Photo of Amandeep S. Kahlon Amandeep S. Kahlon

Aman Kahlon represents owners, general contractors, and subcontractors. His experience ranges over a wide variety of disputes. He advises clients on delay, interference, defective design, and negligence claims. Aman also devotes a significant portion of his practice to contract review, drafting and negotiation…

Aman Kahlon represents owners, general contractors, and subcontractors. His experience ranges over a wide variety of disputes. He advises clients on delay, interference, defective design, and negligence claims. Aman also devotes a significant portion of his practice to contract review, drafting and negotiation; contract and claims administration; and lien and bond law issues.

Additionally, Aman has substantial compliance experience in consumer financial services. He has assisted in the development of audit testing programs and foreclosure policies and procedures for several clients. He also regularly participates in the auditing and remediation of clients’ foreclosure practices.

Read more about Amandeep S. KahlonEmailAman's Linkedin Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo