No Weasel Words in Government Contract Claims Regarding Amount Claimed

By Patrick R. Quigley on March 10, 2020
Email this postTweet this postLike this postShare this post on LinkedIn

No Weasel Words in Government Contract Claims Regarding Amount ClaimedWeasel words: “Words or statements that are intentionally ambiguous or misleading.”  Concise Oxford English Dictionary 1635 (11th ed. rev. 2008).

The Armed Services Board of Contract Appeals (ASBCA) recently dismissed in part Odyssey International, Inc.’s appeal of a government contracts claim for consequential damages because the contractor failed to seek a “sum certain.” Instead, the contractor claimed “at least $15,033,862” (Odyssey International, Inc., ASBCA No. 62062, Jan. 28, 2020 (emphasis added)).  Those weasel words doomed that part of the claim.

What happened?

Odyssey contracted with the U.S. Army Corps of Engineers (the “agency”) to construct an Army depot building. Odyssey determined the building foundation design was unworkable and prepared a revised, more expensive design that was approved, but the agency withheld permission to proceed until a contract modification was executed. The contract modification never came, but two different contracting officer’s representatives gave instructions to proceed with the new foundation work. The agency then cancelled the proposed contract change and stated that it would only pay Odyssey for some of the extra costs incurred. Odyssey submitted a claim of $651,099 to the contracting officer for additional time, subcontract costs, and extended overhead. The contracting officer denied the claim, and Odyssey appealed to the ASBCA.

By way of background, as defined in the Federal Acquisition Regulation, a “[c]laim means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract” (FAR 2.101 (emphasis added)).

In its complaint at the ASBCA, among other arguments, Odyssey sought damages of “at least $15,033,862” under a consequential damages theory. The agency moved for dismissal of that aspect of the claim appeal, arguing that it was speculative, failed to state a sum certain, and had not been previously presented to the contracting officer for a decision.

The ASBCA granted the agency’s motion to dismiss in part, stating, “The [ASBCA] has long held that qualifications to a numerical amount, such as the use of the word ‘approximately,’ ‘no less than,’ or ‘well over’ prevent its consideration as a sum certain…  In fact, [ASBCA] precedent has specifically held that a claim amount prefaced by the specific phrase ‘at least’ fails to state a sum certain.” Alternatively, the ASBCA held that the allegation was a new claim that had not previously been presented to the contracting officer, which also warranted dismissal.

What is the takeaway?

When submitting a claim and, if necessary, a subsequent appeal, the contractor must be specific as to the amount claimed or else risk having some or all of the claim dismissed for failing to state a sum certain.

Photo of Patrick R. Quigley Patrick R. Quigley

Patrick Quigley’s practice is focused on litigating bid protests, contract claims, prime/subcontractor disputes, and small business size protests/appeals at the Government Accountability Office, U.S. Court of Federal Claims, boards of contract appeals, federal agencies, the Small Business Administration, and state courts. He…

Patrick Quigley’s practice is focused on litigating bid protests, contract claims, prime/subcontractor disputes, and small business size protests/appeals at the Government Accountability Office, U.S. Court of Federal Claims, boards of contract appeals, federal agencies, the Small Business Administration, and state courts. He conducts internal investigations and defends clients in False Claims Act litigation, government investigations, and suspension and debarment actions. Patrick conducts due diligence reviews of and advises on the government-contract aspects of business transactions, and counsels on procurement law compliance, federal employee ethics rules, teaming agreements, and conflict-of-interest mitigation plans. View articles by Patrick.

Read more about Patrick R. QuigleyEmailPatrick's Linkedin Profile
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo