Agency Failure to Consider Impact of Corporate Transaction Renders Award Decision Infirm

By Issac Schabes on January 13, 2022
Email this postTweet this postLike this postShare this post on LinkedIn

The acquisition and consolidation of government contractors has become increasingly prevalent in recent years. GAO’s recently released decision in Vertex Aerospace, LLC, B‑420073, B-420073.2, Nov. 23, 2021, serves as an important reminder to contractors that failure to properly update a procuring agency about such transactional activity can have adverse impacts on a pending proposal, even where a transaction is structured/intended to have no impact upon a contractor’s proposed performance. In Vertex, GAO sustained a protest challenging an Air Force task order award due to the agency’s failure to “meaningfully consider” the impact of the awardee’s acquisition by another company during the pendency of the procurement.

In late 2020, DynCorp was awarded an IDIQ contract. Shortly thereafter, Amentum Government Services Holdings, LLC (“Amentum”), acquired all of the outstanding shares of DynCorp’s former parent holding company, resulting in DynCorp becoming Amentum’s wholly owned subsidiary. In December 2020, DynCorp submitted a proposal in response to a task order solicitation under the IDIQ contract. While DynCorp’s proposal was pending and before award, DynCorp submitted documentation to DCMA requesting novation of its IDIQ contract to Amentum. DCMA, in turn, provided a copy of the novation agreement to the Air Force during its evaluation of DynCorp’s proposal. Nonetheless, the Air Force completed that evaluation without considering what impact, if any, the Amentum acquisition would have on DynCorp’s ability to perform. After the Air Force awarded the task order to DynCorp, Vertex protested, alleging, among other things, that the Air Force’s failure to consider that specific question was in error.

GAO sustained the protest. In so doing, GAO noted that DynCorp’s proposal made no mention of its recent acquisition, nor did the agency’s evaluation record or source selection documentation make any reference to the acquisition or its potential effect on DynCorp’s performance. GAO also rejected the Air Force’s post-protest explanation that the acquisition would have no impact on DynCorp’s performance, noting the lack of detail in the contemporaneous record explaining how the integration and consolidation of contract performance activities between the two companies would be accomplished to ensure that the resources and employees needed for the contract would be available. As a result, GAO held the record was insufficient to support a conclusion that the agency meaningfully and reasonably considered the effect of the corporate transaction on the awardee’s ability to perform the task order.

Significantly, GAO stressed that decisions regarding matters of corporate status and restructuring are highly fact-specific, and turn largely on the individual circumstances of the proposed transactions and timing. With that in mind, companies undergoing corporate transactions should work closely with experienced government contracts counsel to determine the best way to minimize the impact such transactions may have on pending proposals, to affirmatively notify agencies of such transactions, and to provide sufficient assurance—prior to an agency’s award decision—that such transactions will not impact the offeror’s proposed performance.

Photo of Issac Schabes Issac Schabes

Issac D. Schabes is an associate in the firm’s Washington, D.C. office, where he is a member of the Government Contracts Group.

Prior to joining the firm, Issac clerked for the Honorable Matthew H. Solomson on the U.S. Court of Federal Claims and…

Issac D. Schabes is an associate in the firm’s Washington, D.C. office, where he is a member of the Government Contracts Group.

Prior to joining the firm, Issac clerked for the Honorable Matthew H. Solomson on the U.S. Court of Federal Claims and the Honorable Robert N. McDonald on the Maryland Court of Appeals. Issac received his J.D., magna cum laude, from the University of Maryland Carey School of Law, where he graduated Order of the Coif and served as an executive editor for the Maryland Law Review. He received numerous awards, including the Judge Simon E. Sobeloff Prize for Excellence in Constitutional Law. During law school, Issac was a member of a low-income taxpayer clinic team that successfully appealed an IRS assessment resulting in a substantial tax liability reduction, and also interned for the Honorable Beryl A. Howell, Chief Judge, on the U.S. District Court for the District of Columbia and the Honorable Marvin J. Garbis on the U.S. District Court for the District of Maryland.

Read more about Issac SchabesEmail
Show more Show less
  • Posted in:
    Government Contracts
  • Blog:
    Government Contracts Legal Forum
  • Organization:
    Crowell & Moring LLP
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo