A Brave New World – Tariffs and Force Majeure

By Christian Dewhurst on February 21, 2025
Email this postTweet this postLike this postShare this post on LinkedIn
tariffs blog image_

My colleague (Graham Quinn) recently wrote an article about the potential financial impact of the impending steel and aluminum tariffs on the construction industry.  See hyperlink: The Impact of President Trump’s Steel and Aluminum Tariffs on the Construction Industry | Texas Construction Law Blog.  One question that we are receiving is whether the ensuing tariffs on steel and aluminum qualify as a force majeure event.  The short answer is it depends on the language of your contract.    

For instance, the AIA 201 defines a force majeure event as a labor disputes, fire, unusual delay in deliveries, unavoidable casualties, adverse weather conditions … or other causes beyond the Contractor’s control.  The ensuing tariffs would arguably qualify as a cause beyond the Contractor’s control.  Other contracts specifically define a force majeure event as “restrictive governmental laws or regulations,” which again is beneficial language seeking to enforce a force majeure provision. 

However, some contacts may not include language that would cover tariffs.  In particular, one contract that I recently reviewed defined a force majeure event as an “Acts of God, war, rebellion, strikes or lockouts, epidemics or health crises, landslides, lightning, earthquakes, fires, named tropical storms.”  There is clearly nothing in this clause that would cover the ensuing tariffs. 

For those in the contract drafting or negotiating phase of an upcoming project, be sure to specifically include the specific term “tariffs” in the defined terms of force majeure events. You should also pay close attention to the remedies afforded by the force majeure provision. Many only permit extensions of time, whereas others allow equitable adjustments to the contract price. Think about key remedies that matter to your company and be sure advocate for them in the contract. 

With the tariffs due to take effect on March 12, 2025, now is a good time to take a look at your force majeure provision and make necessary adjustments to your MSAs.  Gray Reed is happy to help.

Photo of Christian Dewhurst Christian Dewhurst

Christian Dewhurst’s practice is primarily focused on resolving the entire spectrum of claims and litigation that arise during commercial and residential construction projects.

Read more about Christian DewhurstEmailChristian's Linkedin Profile
  • Posted in:
    Business and Commercial
  • Blog:
    Texas Construction Law Blog
  • Organization:
    Gray Reed & McGraw LLP
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo