Skip to content

Menu

LexBlog, Inc. logo
NetworkSub-MenuBrowse by SubjectBrowse by PublisherBrowse by ChannelAbout the NetworkJoin the NetworkProductsSub-MenuProducts OverviewBlog ProBlog PlusBlog PremierMicrositeSyndication PortalsAbout UsContactSubscribeSupport
Book a Demo
Search
Close

Manifest Disregard Discarded: Fifth Circuit Limits Grounds to Vacate Arbitration Awards

By John Mark Goodman & Amandeep S. Kahlon on May 6, 2025
Email this postTweet this postLike this postShare this post on LinkedIn
Manifest Disregard Discarded: Fifth Circuit Limits Grounds to Vacate Arbitration Awards

“Manifest disregard of the law” is no longer a valid basis to challenge arbitration awards, at least not in the federal courts of Texas, Mississippi and Louisiana. Rather, according to the Fifth Circuit’s decision in U.S. Trinity Energy Services v. Southwest Directional Drilling, 2025 WL 1218096 (Apr. 28, 2025, No. 24-10833), the grounds for challenging an arbitration award are limited to those grounds enumerated by Congress in the Federal Arbitration Act. Those include:

  1. where the award was procured by corruption, fraud, or undue means;
  2. where there was evident partiality or corruption in the arbitrators, or either of them;
  3. where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced; or
  4. where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.

9 U.S.C. § 10. 

Manifest disregard of the law, which is not included among the grounds for vacatur in the FAA, requires a party to demonstrate the arbitrator correctly stated or understood a proposition of law but then ignored it. Courts have historically been receptive to this argument and have recognized it as an additional, limited basis to set aside erroneous arbitration awards if none of the above-listed FAA grounds applied. This judge-made doctrine opened the door for losing parties to argue that an arbitrator’s decision should be set aside for ignoring the law in favor of the arbitrator’s “own brand of industrial justice.”  

In U.S. Trinity Energy Services, the Fifth Circuit held that “manifest disregard of the law” is not a valid basis for vacatur and could not be used as “a backdoor for a party to seek judicial review of the arbitrator’s interpretations.” The Fifth Circuit also explained that the fourth statutory basis – where the arbitrators exceed their power – does not include “manifest disregard of the law”:

Grafting “manifest disregard of the law” as a basis for a losing party at arbitration to prevail under § 10(a)(4) would risk tension with Hall Street—and would run headlong into Oxford Health—by forcing us to conduct a less deferential review of a panel’s award than the FAA contemplates. Indeed, adopting Trinity Energy’s reading essentially would rewrite the question a judge must ask from “whether the arbitrators construed the contract at all” to “whether they construed it correctly.”

…

Like our court has held before, “the statutory grounds are the exclusive means for vacatur under the FAA.” Jones, 991 F.3d at 615 (quoting Citigroup, 562 F.3d at 355); see Dream Med. Grp., L.L.C., Old South Trading Co., L.L.C., No. 22-20286, 2023 WL 2366982, at *2 (5th Cir. Mar. 6, 2023) (per curiam) (“These limited circumstances do not include vacating an arbitration award based upon the merits of the claims that were heard by arbitrators.”). The text Congress enacted means what it says throughout § 10(a), and judicial reconfiguration of § 10(a)(4) would betray congressional intent. See Dream Med. Grp., 2023 WL 2366982, at *3 (appellant’s “§ 10(a)(4) arguments amount to an invitation for us to reassess the merits of the Panel’s decision, which does not fall under the limited text of § 10(a)(4) or support vacatur”). In short, we cannot substitute a court panel’s judgment in place of an arbitration panel’s decision by recognizing “manifest disregard of the law” as a basis for vacatur embedded within § 10(a)(4).

The U.S. Trinity Energy Services case involved a subcontract for construction of a natural gas pipeline. The arbitrators awarded the drilling subcontractor over $1.6 million in standby costs caused by COVID-19 and other delays. The prime contractor challenged the award claiming that it was inconsistent with certain provisions of the subcontract. The district court rejected that argument, and the Fifth Circuit affirmed. The arbitrators had considered the evidence, recited the relevant subcontract provisions, and considered their effects. The prime contractor failed to show that the arbitrators exceeded their power “by disregarding the subcontract entirely.” As such, the Fifth Circuit held that the arbitrators’ decision must stand, “however good, bad, or ugly.”

A full copy of the court’s decision is located here.

Photo of John Mark Goodman John Mark Goodman

John Mark Goodman has been with Bradley his entire legal career as a member of Bradley’s Litigation and Construction practice groups. He has an engineering degree from Georgia Tech and a law degree from Virginia. John Mark has had the privilege of representing…

John Mark Goodman has been with Bradley his entire legal career as a member of Bradley’s Litigation and Construction practice groups. He has an engineering degree from Georgia Tech and a law degree from Virginia. John Mark has had the privilege of representing clients throughout the U.S. and abroad in a wide variety of litigation and arbitration matters, including construction disputes, products liability claims, tax appeals, breach of contract/warranty, patent disputes, trade secret theft, and general commercial litigation.

Read more about John Mark GoodmanEmail
Show more Show less
Photo of Amandeep S. Kahlon Amandeep S. Kahlon

Aman Kahlon represents owners, general contractors, and subcontractors. His experience ranges over a wide variety of disputes. He advises clients on delay, interference, defective design, and negligence claims. Aman also devotes a significant portion of his practice to contract review, drafting and negotiation…

Aman Kahlon represents owners, general contractors, and subcontractors. His experience ranges over a wide variety of disputes. He advises clients on delay, interference, defective design, and negligence claims. Aman also devotes a significant portion of his practice to contract review, drafting and negotiation; contract and claims administration; and lien and bond law issues.

Additionally, Aman has substantial compliance experience in consumer financial services. He has assisted in the development of audit testing programs and foreclosure policies and procedures for several clients. He also regularly participates in the auditing and remediation of clients’ foreclosure practices.

Read more about Amandeep S. KahlonEmailAman's Linkedin Profile
Show more Show less
  • Posted in:
    Real Estate & Construction
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

LexBlog, Inc. logo
Facebook LinkedIn Twitter RSS
Real Lawyers
99 Park Row
  • About LexBlog
  • Careers
  • Press
  • Contact LexBlog
  • Privacy Policy
  • Editorial Policy
  • Disclaimer
  • Terms of Service
  • RSS Terms of Service
  • Products
  • Blog Pro
  • Blog Plus
  • Blog Premier
  • Microsite
  • Syndication Portals
  • LexBlog Community
  • Resource Center
  • 1-800-913-0988
  • Submit a Request
  • Support Center
  • System Status
  • Resource Center
  • Blogging 101

New to the Network

  • Tennessee Insurance Litigation Blog
  • Claims & Sustains
  • New Jersey Restraining Order Lawyers
  • New Jersey Gun Lawyers
  • Blog of Reason
Copyright © 2025, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo