"headline": "The Agency’s Email Server Ate My Proposal! – GAO Rejects Challenge to “Late is Late” Rule",
"url": "https://www.lexblog.com/2024/02/15/the-agencys-email-server-ate-my-proposal-gao-rejects-challenge-to-late-is-late-rule/",
"identifier": {
"@type": "PropertyValue",
"name": "LexBlog Library record",
"value": "LEX-WK-ZXFKQ5K1",
"url": "https://www.lexblog.com/lib/ZXFKQ5K1/"
},
"datePublished": "2024-02-15T13:42:04-05:00",
"dateModified": "2024-02-15T10:42:35-05:00",
"author": {
"@type": "Person",
"name": "Emily"
},
"sourceOrganization": {
"@type": "Organization",
"name": "Crowell & Moring LLP"
},
"organizationScope": "at-publication",
"isPartOf": "Government Contracts Legal Forum",
"about": "Administrative and Regulatory · Government Contracts",
"sourceUrl": "https://www.governmentcontractslegalforum.com/?p=5451",
"sourceStability": "may-move"
}