Credibility matters. Here’s another example involving a delay claim on public private partnership delivery method.
The project agreement required claims to be tried by a hearing examiner. The public private partnership developer (for lack of a better term) submitted delay
Kirwin Norris, P.A.
We understand the needs and nuances of the construction process, the complexities of construction law, and the importance of managing and resolving issues in a timely manner to keep your project progressing on time and on budget. Should you be facing litigation, we have an enviable track record of success in state and federal courts. We have in-depth, up-to-the-moment knowledge, along with the valuable industry relationships, that can give you an advantage both on the project site and in the courtroom. Kirwin Norris’ team of dedicated attorneys is located in our Orlando and Fort Lauderdale offices.
Kirwin Norris, P.A. Blogs
Blog Authors
Latest from Kirwin Norris, P.A.
OWNER TAKING ASSIGNMENT OF GENERAL CONTRACTOR’S CLAIMS AGAINST A SUBCONTRACTOR(S)
…
TWO IMPORTANT POINTS REGARDING THE MILLER ACT
A recent Miller Act case, U.S. f/u/b/o Boundless Management Outsourcing Group, LLC v. Endurance Assurance Corp, 2026 WL 2241491 (D. Puerto Rico 2026), confirms two important points when it comes to the Miller Act. In this case, a subcontractor pursued…
SURETY REQUIRING COLLATERAL SECURITY UNDER GENERAL AGREEMENT OF INDEMNITY
In order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and…
LIENOR DEALING WITH “SHOW CAUSE” SUMMONS BY CONDOMINIUM UNIT OWNER
One of the statutory vehicles to shorten a construction lienor’s statute of limitations to foreclose on a construction lien is through a “show cause” summons that essentially requires the lienor to foreclose on the lien within 20 days from receipt…
WHAT IS THE INDEPENDENT TORT DOCTRINE? NEW CASE EXPLAINS…
Florida’s Sixth District Court of Appeals in Atout v. HHM Land Trust Dated October 29, 2013, 51 Fla.L.Weekly D1569a (Fla. 6th DCA 2026) recently included an extensive discussion on Florida’s independent tort doctrine. The independent tort doctrine is an important…
FEDERAL BID PROTEST STANDARD OF REVIEW AND DISPARATE TREATMENT WITH RATINGS
A recent decision out of the Federal Claims Court explains the post-award bid protest standard of review.
In Massman Construction Co. v. U.S., 2026 WL 1971985 (Fed.Cl. 2026), a protestor brought a post-award bid protest after the Army Corps of…
CONSTRUCTION LIENS: LIENING FOR AMOUNTS NOT YET TECHNICALLY DUE DOES NOT MEAN LIEN IS FRAUDULENT
A 2024 bankruptcy ruling, In re Edgewater Construction Group, Inc., 657 B.R. 668 (S.D.Fla. 2024), touched upon an interesting issue when it comes to construction liens. Is a construction lien fraudulent simply because the lien includes amounts not yet due?…
INSUFFICIENT NOTICE OF COMMENCEMENT AND CONSTRUCTION LIEN RIGHTS
When a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice…
DOCTRINE OF SUBSTANTIAL PERFORMANCE WHEN IT COMES TO PAYMENT
A recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapper’s attendance. The first payment was made. The second payment was…