US District Court for Middle District of Pennsylvania Holds Course of Performance May Vitiate Partial Payment Releases and Delay Costs May Be Recovered Under Federal Miller Act Payment Bond
By Constructlaw
U.S. ex rel Pioneer Construction v. Pride Enterprises 2009 U.S. Dist. LEXIS 110935 (M.D. Pa., November 27, 2009) The court denied the contractor’s claim for summary judgment, which was based…
Constructlaw®
Texas Court of Appeals Holds that Contractor Released Claim for Additional Costs by Accepting Final Payment from Owner
By Constructlaw
McKinney & Moore, Inc. v. City of Longview, Texas 2009 Tex. App. LEXIS 9299 (Tex. App., Dec. 8, 2009) The Court of Appeals of Texas for the Fourteenth District held…
Constructlaw®
Pennsylvania Supreme Court Holds Utility Not Liable to Excavation Contractor for Economic Loss Resulting from Inaccurately Marking Location of Gas Lines
By Constructlaw
Excavation Technologies, Inc. v. Columbia Gas Co. of PA 2009 Pa. LEXIS 2794 (Pa., December 29, 2009) The Pennsylvania Supreme Court held that a utility company’s failure to properly mark…
Constructlaw®
US District Court Holds “Gist of the Action” Doctrine Bars Parallel Negligence Claim for Property Damage Where the Essence of Plaintiff’s Claim Was for Breach of Contract
By Constructlaw
Federal Insurance Co. v. Philotimo, Inc. 2009 U.S. Dist. Lexis 108105 (W.D.P.A. Nov. 19, 2009) Homeowner hired defendant to inspect and clean its fireplace and chimney after observing chunks of…
Constructlaw®
Second Circuit Holds Arbitrators Cannot, Under the Federal Arbitration Act, Compel Pre-Hearing Discovery of Documents of Third Parties, Except That Production May be Compelled at a Preliminary Hearing Before an Arbitrator
By Constructlaw
Life Receivables Trust v. Syndicate 102 at Lloyd’s of London 2008 U.S. App. LEXIS 24977 (Nov. 25, 2008) The Second Circuit held that section 7 of the Federal Arbitration Act…
Constructlaw®
Pennsylvania Supreme Court Holds That, Absent Express Reservation Of Rights, Release Of Contractor Also Discharges Surety
By Constructlaw
Kiski Area Sch. Dist. v. Mid-State Surety Corp. 2008 Pa. LEXIS 2260 (Dec. 17, 1988) Kiski Area School District (“the District”) entered into an agreement with contractor, Lanmark, for the…
Constructlaw®
Vermont District Court Declines To Apply Exception To Economic Loss Rule To Contractor’s Claims Against Architect
By Constructlaw
Hunt Construction Group, Inc. v. Brennan Beer Gorman / Architects, P.C. 2008 U.S. Dist. LEXIS 93754 (D. Vt. 2008) In declining to apply an exception to the economic loss rule,…
Constructlaw®
United States District Court in New Jersey Considers Effect of Waiver of Consequential Damages and Damages Cap on Indemnification Provisions Contained in Architect’s Contract
By Constructlaw
Atlantic City Associates LLC v. Carter & Burgess Consultants, Inc. 2008 U.S. Dist. LEXIS 93684 (D.N.J. Nov. 13, 2008) The United States District Court for the District of New Jersey…
Constructlaw®
United States District Court in Virginia Holds That Prime Contract Provision Concerning Accrual of Statute of Limitations “Flowed Down” to Afford Subcontractor Defense to Defective Work Claim
By Constructlaw
Steadfast Insurance Co v. Brodie Contractors, Inc. 2008 U.S. Dist. LEXIS 88448 (October 31, 2008 W.D. Va.) Steadfast Insurance Co., as subrogee of Skanska USA Building Co., the general contractor,…
Constructlaw®
Wyoming Court Upholds Delay Damage Award To Contractor For Owner’s Breach Of Implied Covenant Of Good Faith And Fair Dealing Even Though The Owner Did Not Breach Contract’s Express Terms
By Constructlaw
City of Gillette v. Hladky Construction, Inc. 2008 Wyo. LEXIS 139 (November 14, 2008) The Supreme Court of Wyoming upheld an award to a Contractor of more than one million…