    Liquidated Damages Clause Bars Separate Recovery for Lost Power Sales Even Though Loss is Many Times Greater Than Liquidated Damage Amount – Correction Damages, However, Are Separately Recoverable

    By Constructlaw

    El Dorado Irrigation Dist. v. Traylor Bros., Inc. No. 03-949, 2006 U.S. Dist. LEXIS 1354 (E.D. Cal. Jan. 4, 2006) In El Dorado Irrigation Dist. v. Traylor Bros., Inc., No.…

  2. Constructlaw®

    Contractor’s Continued Acceptance of Subcontractor’s Performance Waives Right To Terminate

    By Constructlaw

    Ed Kimber Heating & Cooling, Inc. v. Travelers Casualty & Surety Co. No. 3:03cv2111 (SRU), 2006 U.S. Dist. LEXIS 3323 (D. Conn. Jan. 26, 2006) Trataros Construction, Inc. (“Trataros”), the…

  3. Constructlaw®

    Statute Of Limitations Not Tolled by Discovery Rule under AIA Article 9.3

    By Constructlaw

    Gustine Uniontown Assocs., LTD v. Anthony Crane Rental, Inc. 2006 PA Super 12 (Pa. Super. Ct. 2006) In conjunction with its construction of a shopping mall over a non-functioning coal…

  4. Constructlaw®

    Engineer’s Decision Did Not Constitute an Arbitration Award

    By Constructlaw

    City of Ferndale v. Florence Cement Co 2006 Mich. App. LEXIS 129, No. 254572 (January 17, 2006) In City of Ferndale v. Florence Cement Co. and Hartford Casualty Insurance Co.,…

  5. Constructlaw®

    Contemporaneous Expression of Intent to Seek Additional Compensation Saves Pass-Through Claim from Bar of Severin Doctrine Despite Accord and Satisfaction Language in Change Orders

    By Constructlaw

    Appeal of M.A. Mortenson Company No. 53761, 2006 ASBCA LEXIS 4 (ASBCA Jan. 26, 2006) Appeal of M.A. Mortenson Company, No. 53761, 2006 ASBCA LEXIS 4 (ASBCA Jan. 26, 2006)…

  6. Constructlaw®

    Payment Bond Does Not Cover Major Repairs to Heavy Construction Equipment Akin to Capital Improvements

    By Constructlaw

    Beckwith Machinery Company v. Asset Recovery Group, Inc. 2005 Pa. Super. 429, 2005 Pa. Super. LEXIS 4276 (Pa. Super. Ct. 2005) In Beckwith Machinery Company v. Asset Recovery Group, Inc.,…

  7. Constructlaw®

    Acceptance of Subcontractor’s Work by General Contractor Relieves the Subcontractor of Liability to Employee of Following Subcontractor

    By Constructlaw

    Webber v. McBride & Sons Contracting Co. No. ED86076, 2005 Mo. App. LEXIS 1846 (Mo. Ct. App. Dec. 13, 2005) A painter suffered personal injuries after falling through a stairwell…

  8. Constructlaw®

    Flow Down Provision Requires Subcontractor to Proceed During Pendency of Dispute Over Extra Work – A Dispute The Subcontractor Loses as a Result of Course of Performance

    By Constructlaw

    LBL Skysystems (USA), Inc. v. APG-America, Inc. No. 02-5379, 2005 U.S. Dist. LEXIS 19065 (E.D.Pa. Aug. 31, 2005) In LBL Skysystems (USA), Inc. v. APG-America, Inc., No. 02-5379, 2005 U.S.…

  9. Constructlaw®

    Massachusetts Court Equates Change in Construction Sequence with a Change in Scope, Awarding Inefficiency Damages Based on Modified Total Cost Claim

    By Constructlaw

    Daniel Marr & Son Co. v. Coreslab Structures, Inc. et al. No. 03-1880, 2005 Mass. Super. LEXIS 545, (Mass. Supp. Nov. 21, 2005) In Daniel Marr & Son Co. v.…

  10. Constructlaw®

    Maryland Court Holds that Subcontract Requirement of Passing Through Subcontractor’s Claims Against Owner Does Not Create “Pay-When-Paid” Condition; Prime Contractor Remains Liable for Payment

    By Constructlaw

    Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc. 165 Md. App. 262, 885 A.2d 381, 2005 Md. App. LEXIS 273 (Maryland Ct Spec. App., October 31, 2005) Richard…