Federal Circuit Clarifies Narrow Scope of Torncello and Proper Standard for Reviewing Termination for Convenience
By Constructlaw
Krygoski Constr. Co., Inc. v. United States, 94 F.3d 1537 (Fed. Cir. August 1, 1996) Government need not show "changed circumstances" in order to justify convenience termination; rather, termination is…
Constructlaw®
Federal Circuit Court Of Appeals Addresses Definition of "Claim" Under The Contract Disputes Act
By Constructlaw
Ellett Constr. Co., Inc. v. United States, 93 F.3d 1537, U.S. App. LEXIS, August 26, 1996 A settlement proposal in response to a termination for the convenience of the Government…
Constructlaw®
Seventh Circuit Holds that Indian Tribe Agreed to Waive Sovereign Immunity
By Constructlaw
Sokaogon Gaming Enterprise Corp. v. Tushie-Montgomery Assocs, Inc., 86 F.3d 656, 1996 U.S. App. LEXIS 13399 (7th Cir. June 5, 1996) District Court erred in granting summary judgment in favor…
Constructlaw®
Seventh Circuit Rules That Forum Selection Clause in Construction Contract Is Enforceable Under Illinois Law
By Constructlaw
Roberts & Schaefer Co. v. Merit Contracting, Inc., 99 F.3d 248, 1996 U.S. App. LEXIS 28280 (U.S. Ct. of Appeals, 7th Cir.) Contract between the parties contained an enforceable forum…
Constructlaw®
The Supreme Court of Alaska Held That a Contractor’s Failure to Comply with the Contractual Notice Provisions Barred Its Claim as a Matter of Law
By Constructlaw
Neal & Co., Inc. v. City of Dillingham and CH2M Hill Northwest, Inc., 923 P.2d 89 (Alaska 1996) In February of 1987, the City of Dillingham ("City") solicited bids for…
Constructlaw®
Federal Circuit Court of Appeals Denies Contractor Recovery Because Alleged "Differing Site Condition" Did Not Exist at Time of Contract Award.
By Constructlaw
Olympus Corp. v. United States, 98 F.3d 1314, 1996 U.S. App. LEXIS 27509 (U.S. Fed. Cir., Oct. 23, 1996) Standard "Differing Site Conditions" clause in Government contract requires, as a…
Constructlaw®
The Florida Court of Appeal for the Fifth District Reversed the Trial Court’s Imposition of Delay Damages When the Plaintiff’s Expert "Assumed" Certain Expenses and Therefore Lacked Sufficient Factual Basis to Express His Opinions
By Constructlaw
Central Florida Plastering and Development, et al. v. Sovran Constr. Co., Inc., 679 So.2d 1226 (1996) Sovran Construction Company, Inc. ("Sovran") contracted with the Orange County School Board ("School Board")…
Constructlaw®
Utah Supreme Court considers non-contractual liability of contractors for damages resulting from defective work
By Constructlaw
Interwest Construction v. A.H. Palmer & Sons, 292 Utah Adv. Rep. 27, 1996 Utah LEXIS 44 (Utah June 14, 1996) The Supreme Court of Utah held that the intermediate court…
Constructlaw®
Eleventh Circuit reverses grant of summary judgment in favor of contractor on basis of releases executed by subcontractor.
By Constructlaw
Allgood Electric Co. v. Martin K. Eby Constr. Co., 85 F.3d 1547, 1996 U.S. App. LEXIS 15252 (11th Cir. June 25, 1996) Under Georgia law, subcontractor's release of all claims…
Constructlaw®
District Court for District of Columbia Declares Liquidated Damages Clause Unenforceable
By Constructlaw
Kingston Constructors, Inc. v. Washington Metropolitan Area Transit Authority, 1996 U.S. Dist. LEXIS 8427 (D.D.C. June 6, 1996) Corps of Engineers Board of Contract Appeals erred in reducing amount of…