Washington Energy Report
FERC Denies Complaint Against PJM Relating to Interconnection Study Cycle 01
By Peter Fasoli*, Alexander Kaplen
On September 24, 2026, FERC denied a complaint filed by Oklo, Inc. (Oklo) against PJM Interconnection, L.L.C. (PJM) alleging that PJM unlawfully administered the interconnection process to Oklo’s 750-megawatt project…
Washington Energy Report
FERC Denies Complaint Against PJM’s Transition Cycle No. 1 Process
On May 21, 2026, FERC denied a complaint filed by Gaston Green Acres Solar, LLC (Gaston) and Bethel NC Hwy 11 Solar, LLC (Bethel) (collectively, with Gaston, Complainants) against PJM…
Washington Energy Report
FERC Approves SPP’s Consolidated Planning Process
By Alex Spratley, Antonia Douglas
On March 19, 2026, FERC approved Southwest Power Pool, Inc.’s (SPP) proposal to establish a Consolidated Planning Process (CPP) framework to streamline its regional transmission planning and generator interconnection process.…
Washington Energy Report
PJM Proposes Expedited Generator Interconnection Track
On February 27, 2026, PJM Interconnection, L.L.C. (PJM) filed revisions to its Open Access Transmission Tariff (Tariff) to establish an Expedited Interconnection Track process for Generating Facilities (EIT Process). According…
Washington Energy Report
MISO to Expand Number of Interconnection Requests it Can Study on Expedited Basis
By Alex Spratley, Dixon Wallace
On November 25, 2025, FERC accepted the Midcontinent Independent System Operator, Inc.’s (MISO) proposal to expand the number of interconnection requests MISO may study under its temporary, fast-tracked generator interconnection…
Washington Energy Report
FERC Reaffirms MISO Interconnection Queue Cap on Rehearing
By Quintessa Davis, Antonia Douglas
On May 27, 2025, FERC addressed arguments raised on rehearing of a January 30, 2025 order, which accepted the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposal to modify its generator…
Latham.London
Ofgem Approves Great Britain’s Grid Connections Reform
The reform aims to prioritise “ready” and “needed” projects for grid connection. By Conrad Andersen, Simon J. Tysoe, John Guccione, Tom Bartlett, and Evelyne Girio On 15 April 2025, the…
LawDroid Manifesto
Daily News: April 10, 2025
By Tom Martin
Hey there friends👋! In today’s edition, you’re getting 5 🆕 news items and my take on what it all means. That’s it — delivered to your inbox, daily.Subscribe to LawDroid…
GT London Law Blog
UK Grid Connection Reforms: Breaking the Bottleneck
By Shashank Krishna, Harshita Khurana‡, Tom Hilton ˘
The UK is transforming its grid connection system to address a backlog of over 739 GW of projects, aiming to streamline access and reduce delays.
E2 Law Blog
UK Grid Connection Reforms: Breaking the Bottleneck
By Shashank Krishna, Harshita Khurana‡, Tom Hilton ˘
The UK is transforming its grid connection system to address a backlog of over 739 GW of projects, aiming to streamline access and reduce delays.