Topic
New Source Review
36 published works
Environmental and Energy Brief
EPA Proposal Could Reduce New Source Review-Related Delays for Major Construction Projects
By Brittany A. Bolen, Caleb J. Bowers, Riley Desper
The U.S. Environmental Protection Agency (EPA) recently proposed a rule that could allow project developers of data centers, energy projects, and other facilities to begin certain site-development and infrastructure activities…
HeplerBroom Blog
USEPA Announces Revised Interpretation of “Begin Actual Construction” under New Source Review Regulations
On March 25, 2020, the United States Environmental Protection Agency (“USEPA”) published on its website a draft memorandum entitled “Interpretation of ‘Begin Actual Construction’ Under the New Source Review Preconstruction…
Environmental Law & Policy Monitor
EPA Engages in Flurry of NSR-Related Actions as 2019 Draws to a Close
By Angela Levin, Mack McGuffey, Melissa Horne
EPA’s New Source Review (NSR) reform efforts have been in full swing over the past month or so as the Agency released two final guidance documents, issued a pre-publication version…
The Nickel Report
Federal Government Drops NSR Enforcement Case Against Luminant, Avoiding Another Nail in the Coffin of NSR Enforcement for Ancient Projects
In October 2018, the Fifth Circuit joined the overwhelming majority of US courts of appeals in ruling the statute of limitations bars civil penalties for alleged NSR violations. But, in…
Energy & Environmental Law Adviser
Emission Decreases Count: EPA Proposes Rule to Codify Approach to NSR Project Emissions Accounting
On August 9, 2019, the EPA plans to publish a proposed rule to codify the current interpretation of New Source Review (NSR) Project Emissions Accounting. The rule would explicitly allow…
EHS Law Insights
What does the Pennsylvania EHB aggregation decision and opinion mean for your business?
By Forrest M. Smith, Jennifer A. Smokelin
Clean Air Council v. Department of Environmental Protection and Sunoco Partners Marketing & Terminals, L.P., EHB Dkt. No. 2016073L (Adjudication Jan. 9, 2019) On January 9, 2019, the Pennsylvania Environmental Hearing Board…
Environmental Law & Policy Monitor
EPA Re-Finalizes Clarification on When Two Projects Must Become One
When must two different activities be grouped together to determine whether they trigger New Source Review permitting? That is the question EPA answered last month after many years of debate…
Energy & Environmental Law Blog
USEPA Concludes Reconsideration of 2009 NSR Project Aggregation Interpretation
By Mac Taylor
On November 7, 2018, USEPA concluded its reconsideration (“2018 Reconsideration Action”) of a January 15, 2009 interpretation regarding NSR project aggregation (the “2009 NSR Aggregation Action”). See 74 Fed.Reg. 2376…
The Nickel Report
NSR Enforcement Litigation: What You Need to Know
The New Source Review (NSR) program of the Clean Air Act requires major stationary sources to go through an extensive, time-consuming, and expensive review and permitting process prior to construction.…
The Nickel Report
NSR Reform — EPA’s ACE Proposal
Our regulatory state is founded on the principle that regulated parties must have notice of their compliance obligations. Laws or regulations that fail to give fair notice violate due process…