  1. Washington Energy Report

    FERC Judge Rules that Four Solar Generators Interconnected at the Distribution Level Are Ineligible to Receive Reactive Power Compensation Under PJM’s Tariff

    By S. Jennifer Panahi, Miles Kiger

    On July 15, 2022, a FERC Administrative Law Judge (“Presiding Judge”) issued an initial decision in a proceeding involving the “threshold” issue of whether four solar generating facilities (collectively, “Facilities”)…

  2. Energy Law Blog

    FERC Seeks Comments on Potential Alternative Reactive Power Compensation Mechanisms in Reactive Power Capability Compensation, 177 FERC ⁋ 61,118 (2021) (“NOI”)

    By Mark Sundback, Andrew Mina

    Introduction: On November 18, 2021, the Federal Energy Regulatory Commission (“FERC” or “Commission”) issued a notice of inquiry seeking comments on various aspects of currently accepted reactive power compensation mechanisms…

  3. Washington Energy Report

    FERC Rejects Reactive Compensation Settlement, Finding Methodology Flawed

    By Sidney Villanueva, Miles Kiger

    On September 23, 2021, FERC issued an order rejecting a unilateral offer of settlement regarding the compensation for reactive power by Panda Hummel Station LLC (“Panda”) under Schedule 2 of…