Land Use – Transportation Impact Fees

By Eric S. Goldberg on October 28, 2015
Email this postTweet this postLike this postShare this post on LinkedIn

Metro Bank v. Board of Commissioners of Manheim Township (Pa. Commonwealth Court 2015) dealt with the appropriate calculation for a transportation impact fee. Metro Bank was approved to build a bank in Manheim Township, and was required to pay an estimated transportation impact fee prior to the start of construction. This dispute is due to the amount of the transportation impact fee to be paid.

Metro Bank’s consultant determined that the new bank’s location would generate 110 peak hour trips with a pass-by rate of 57%. Thus, it was expected that 63 of the 110 peak hour trips would be generated from vehicles that were already driving and passing by the new development. A transportation impact fee is intended to offset the strain on a municipality’s roads when the development is installed in an area.

Manheim Township disagreed with Metro Bank’s estimation, and determined that the impact fee should be based on all of the 110 peak hour trips. The bank countered that the impact fee should only be based on the 47 additional trips into the development not resulting from vehicles that were already on the road.

The Court looked at the Administration of Impact Fee provision contained in Section 505-A of the Municipalities Planning Code and determined that nothing in that section required the municipality to exclude pass-by trips. Moreover, the Court determined that Metro Bank’s interpretation would lead to an inappropriate result because, by excluding pass-by traffic, the revenues generated by the impact fee would fall significantly short of the Township’s total costs.

Additionally, under Metro Bank’s calculation, the initial developer would pay for an unfairly high percentage of the increase in vehicular traffic to an area. Thus, the Court held that the impact fee should be determined by multiplying the per-cost trip multiplier by peak hour trips attributed to the new development, with no exclusion for pass-by traffic.

Photo of Eric S. Goldberg Eric S. Goldberg

Eric S. Goldberg is a Shareholder at Stark & Stark and member of its Real Estate and Business & Transactional Groups. Mr. Goldberg practices in both the Lawrenceville/Princeton and Yardley offices. He focuses on various types of transactional law, with an emphasis in…

Eric S. Goldberg is a Shareholder at Stark & Stark and member of its Real Estate and Business & Transactional Groups. Mr. Goldberg practices in both the Lawrenceville/Princeton and Yardley offices. He focuses on various types of transactional law, with an emphasis in the areas of real estate, land use, and business law.

Read more about Eric S. GoldbergEmail
Show more Show less
  • Posted in:
    Real Estate & Construction
  • Blog:
    Pennsylvania Law Monitor
  • Organization:
    Stark & Stark
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo