You’ve Gotta Fight For Your Right To Get Paid: The Right To Stop Work

By Amy Elizabeth Garber & Eric A. Frechtel on July 13, 2021
Email this postTweet this postLike this postShare this post on LinkedIn

You’ve Gotta Fight For Your Right To Get Paid: The Right To Stop WorkA contractor is halfway through the (timely) completion of a project and the owner’s payment is late. Days, weeks go by, and now the contractor is incurring all the costs of the work without any compensation. It might be tempting to simply walk off the job, but bear in mind that legally speaking, that might constitute the “first breach,” even if the owner is late on payment. Enter: the stop work clause.

The optimal stop work clause clearly provides the contractor the right to suspend its work if the owner fails to pay after a certain amount of time, and then get a time extension for any delays resulting from the suspension. The standard AIA language has it all and can be easily tailored to a contract’s payment mechanisms:

If the Architect does not issue a Certificate for Payment, through no fault of the Contractor, within seven days after receipt of the Contractor’s Application for Payment, or if the Owner does not pay the Contractor within seven days after the date established in the Contract Documents, the amount certified by the Architect or awarded by binding dispute resolution, then the Contractor may, upon seven additional days’ notice to the Owner and Architect, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor’s reasonable costs of shutdown, delay and start-up, plus interest as provided for in the Contract Documents.

Remember, the more details the parties include upfront in the contract, the less there is to argue over later.

Note that there are arguments a contractor can make to justify walking off the job: it was impossible to continue working without payment for labor and materials; the owner’s nonpayment was such an egregious breach that it nullified the contract; or, major subcontractors walked off, too. While some of these may win the day, without clear contract language justifying stopping work, doing so is a gamble.

Photo of Amy Elizabeth Garber Amy Elizabeth Garber

Amy Garber focuses her practice on construction and government contracts, and has significant experience in commercial litigation. She handles construction, arbitration, and litigation matters in the District of Columbia, Virginia, and the Fourth Circuit. In her construction practice, Amy has represented and counseled…

Amy Garber focuses her practice on construction and government contracts, and has significant experience in commercial litigation. She handles construction, arbitration, and litigation matters in the District of Columbia, Virginia, and the Fourth Circuit. In her construction practice, Amy has represented and counseled contractors in cases involving federal and state Miller Act and complex payment disputes, and effected removal, settlement, and/or dismissal of various claims. View articles by Amy

Read more about Amy Elizabeth GarberEmailAmy's Linkedin Profile
Show more Show less
Photo of Eric A. Frechtel Eric A. Frechtel

Eric Frechtel practices in the area of construction and government contracts. He represents general contractors, subcontractors, sureties, and owners, in both the prosecution and defense of claims on large public and private construction projects. He has significant litigation experience before both state and…

Eric Frechtel practices in the area of construction and government contracts. He represents general contractors, subcontractors, sureties, and owners, in both the prosecution and defense of claims on large public and private construction projects. He has significant litigation experience before both state and federal courts, including both bench trials and jury trials, and he has considerable experience in construction arbitration as well. View articles by Eric

Read more about Eric A. FrechtelEmailEric's Linkedin Profile
Show more Show less
  • Posted in:
    Real Estate & Construction
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

LexBlog, Inc. logo
Facebook LinkedIn Twitter RSS
Real Lawyers
99 Park Row
  • About LexBlog
  • Careers
  • Press
  • Contact LexBlog
  • Privacy Policy
  • Editorial Policy
  • Disclaimer
  • Terms of Service
  • RSS Terms of Service
  • Products
  • Blog Pro
  • Blog Plus
  • Blog Premier
  • Microsite
  • Syndication Portals
  • LexBlog Community
  • 1-800-913-0988
  • Submit a Request
  • Support Center
  • System Status
  • Resource Center

New to the Network

  • Pro Policyholder
  • The Way on FDA
  • Crypto Digest
  • Inside Cybersecurity & Privacy Law
  • La Oficina Legal Ayala Hernández
Copyright © 2022, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo