Summary of FERC’s April 2022 NOPR on Transmission Planning, Cost Allocation, and Generator Interconnection

By Adrienne Thompson, Sidney Villanueva, Russell Kooistra, Miles Kiger, Katherine O'Konski & Antonia Douglas on April 29, 2022
Email this postTweet this postLike this postShare this post on LinkedIn

On April 21, the Federal Energy Regulatory Commission (FERC or Commission) released its Notice of Proposed Rulemaking (NOPR) to reform its policies regarding Regional Transmission Planning and Cost Allocation. The NOPR follows from an Advanced Notice of Proposed Rulemaking (ANOPR) on these reforms, which FERC issued in July 2021. Representing FERC’s most significant action on transmission planning and cost allocation in more than a decade, the NOPR outlines six major proposals:

  • Regional Transmission Planning: The NOPR proposes to require transmission planning processes to engage in long-term planning and evaluate transmission needs-driven changing resources and demands.
  • Dynamic Line Ratings and Advanced Power Flows Devices: The NOPR proposes to require that regional transmission planning processes consider dynamic line ratings and advanced power flows.
  • Transmission Cost Allocation and State Participation/Agreement: The NOPR proposes to require transmission providers to seek agreement regarding cost allocation from relevant state entities within the applicable transmission planning region and include in their Open Access Transmission Tariffs (OATTs): (1) an ex ante regional cost allocation method; (2) a ex post process for achieving state agreement for a particular planned facility; or (3) some combination thereof. The NOPR also proposes to require transmission providers to seek state agreement on which of these three options to use. The NOPR also proposes to have transmission providers file state-agreed cost allocations for specific projects with FERC under Section 205.
  • Construction Work in Progress (CWIP) Incentive: The NOPR proposes to prohibit the CWIP incentive for transmission facilities selected in regional plans for purposes of cost allocation.
  • Federal Right of First Refusal (ROFR): The NOPR proposes to permit incumbent transmission providers the use of a federal ROFR in regional plans for purposes of cost allocation on the condition that the facilities be jointly owned.
  • Transparency and Coordination: The NOPR proposes enhanced transparency and coordination requirements within, and between, regional and local transmission planning processes so as to “right-size” replacement transmission facilities.

A link to the full summary of the NOPR can be found here. A copy of the order can be found here. Comments on the proposed reforms, which are discussed further below, are due within 75 days of the date that the NOPR is published in the Federal Register.

Photo of Russell Kooistra Russell Kooistra

Russell Kooistra counsels an array of energy companies on various issues related to natural gas and electricity markets. Russell uses his in-depth knowledge of Federal Energy Regulatory Commission (FERC) policy and regulations to advise clients on complex regulatory matters.

Read more about Russell KooistraEmail
Photo of Antonia Douglas Antonia Douglas
Read more about Antonia DouglasEmail
  • Posted in:
    Energy
  • Blog:
    Washington Energy Report
  • Organization:
    Troutman Pepper Locke
  • Article: View Original Source

LexBlog, Inc. logo
Facebook LinkedIn Twitter RSS
Real Lawyers
99 Park Row
  • About LexBlog
  • Careers
  • Press
  • Contact LexBlog
  • Privacy Policy
  • Editorial Policy
  • Disclaimer
  • Terms of Service
  • RSS Terms of Service
  • Products
  • Blog Pro
  • Blog Plus
  • Blog Premier
  • Microsite
  • Syndication Portals
  • LexBlog Community
  • Resource Center
  • 1-800-913-0988
  • Submit a Request
  • Support Center
  • System Status
  • Resource Center
  • Blogging 101

New to the Network

  • Tennessee Insurance Litigation Blog
  • Claims & Sustains
  • New Jersey Restraining Order Lawyers
  • New Jersey Gun Lawyers
  • Blog of Reason
Copyright © 2025, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo