Government Contractors Working “At Risk” During a Shutdown: Key Considerations

By Aron C. Beezley, Nathaniel J. Greeson & Steven C. Herrera on October 15, 2025
Email this postTweet this postLike this postShare this post on LinkedIn
Government Contractors Working “At Risk” During a Shutdown: Key Considerations

Table of Contents

  • What Does Working “At Risk” Mean?
  • The Anti-Deficiency Act and Lack of Authority to Obligate Funds
  • Risks of Continuing Performance
  • Circumstances Where Work May Continue
  • Best Practices for Contractors
  • Seeking Equitable Adjustments After the Shutdown
  • Conclusion

When a federal government shutdown occurs, contractors often face difficult decisions about whether to continue performance on certain contracts. In some cases, contractors may feel pressure — from either operational necessity or the government’s informal requests — to keep working despite funding lapses. However, doing so can expose a contractor to significant financial and legal risks.

Below, we outline what it means to perform “at risk” during a shutdown, and key factors government contractors should carefully evaluate before making that decision.

Link to What Does Working “At Risk” Mean? What Does Working “At Risk” Mean?

A contractor is considered to be working “at risk” when it continues to perform under a government contract without a valid funding obligation in place — meaning there is no appropriated funding legally available to pay for the work being performed.

During a government shutdown, this situation often arises because agencies cannot obligate new funds or modify existing contracts. Even if agency personnel urge a contractor to continue performance, such direction may not constitute a legally binding commitment if the government lacks the authority to incur new obligations during the lapse in appropriations.

Link to The Anti-Deficiency Act and Lack of Authority to Obligate Funds The Anti-Deficiency Act and Lack of Authority to Obligate Funds

The Anti-Deficiency Act (31 U.S.C. §§ 1341 et seq.) prohibits federal employees from obligating funds that have not been appropriated by Congress. As a result, government personnel generally cannot authorize work or accept free services from a contractor during a shutdown, unless the activity is specifically exempted (for example, work supporting national security, the protection of life and property, or certain funded programs).

If a contractor continues work without a valid obligation, payment may be delayed — or, in the worst case, unrecoverable — absent later ratification by an authorized contracting officer or new appropriations legislation. Likewise, because the Anti-Deficiency Act is the only fiscal statute to impose both civil and criminal penalties upon government personnel (not contractors) for violations, contractors should generally try to avoid placing their government partners in precarious situations by continuing to work without authorization.

Link to Risks of Continuing Performance Risks of Continuing Performance

Working “at risk” carries several potential consequences, including:

  • No guarantee of payment – The government may refuse to pay for work performed without an authorized obligation. This risk is especially true for contracts containing FAR 52.232-18, which limits government liability for payment in the absence of available funding.
  • Cost disallowance – If the work is later deemed unauthorized, the contractor may not be able to recover its costs under the contract.
  • Contractor responsibility – Continuing performance could lead to disputes over whether costs were “reasonable” and may complicate subsequent equitable adjustment or claims.
  • Increased audit scrutiny – Auditors and contracting officers may closely examine any costs incurred during a shutdown period. Those costs may also be questioned in contracts requiring compliance with FAR Part 31.

Link to Circumstances Where Work May Continue Circumstances Where Work May Continue

There are situations where federal contractors may legitimately continue performance during a shutdown, including:

  • Fully funded contracts – If the contract was fully funded before the shutdown, performance may generally continue.
  • Multi-year or no-year appropriations – Certain contracts supported by multi-year or no-year funds may not be affected.
  • Exempted activities – Work deemed essential to the protection of life, property, or national security may proceed, though such determinations should be clearly documented.

Contractors should confirm the funding status of their contracts with the contracting officer in writing before proceeding with any performance during a funding lapse.

Link to Best Practices for Contractors Best Practices for Contractors

To mitigate risk, government contractors should consider the following steps:

  • Obtain written direction – Request written confirmation from the contracting officer regarding whether to stop or continue work.
  • Document communications – Keep thorough records of all communications with the government during the shutdown period.
  • Segregate costs – Track any costs incurred during the shutdown separately in case of later funding or claim disputes.
  • Assess business impact – Evaluate the financial risk of continuing performance without guaranteed payment.
  • Develop internal shutdown protocols – Establish internal policies and communication plans for responding to shutdowns and funding lapses.

Link to Seeking Equitable Adjustments After the Shutdown Seeking Equitable Adjustments After the Shutdown

If a contractor has performed work “at risk” based on government direction during a shutdown, it may later seek equitable adjustments or pursue a claim under the Contract Disputes Act (41 U.S.C. §§ 7101 et seq.) — particularly if the government benefits from the continued performance or subsequently ratifies the work. However, recovery is not automatic, and contractors must be prepared to demonstrate the government’s constructive or implied authorization and the reasonableness of their actions.

Link to Conclusion Conclusion

Government shutdowns create significant uncertainty for contractors, particularly regarding whether and when to continue work. While the desire to maintain good relationships with agency customers is understandable, performing “at risk” can create financial exposure. It can also expose government personnel to potential violations of the Anti-Deficiency Act.

To mitigate these risks, federal contractors should proceed cautiously, seek clear written direction from authorized contracting officials, and consult experienced government contracts counsel before undertaking any performance during a lapse in appropriations.

If you have any questions about any of the foregoing, please do not hesitate to contact Aron Beezley, Nathaniel Greeson, or Steven Herrera.

Photo of Aron C. Beezley Aron C. Beezley

Aron Beezley is the co-leader of Bradley’s nationally ranked Government Contracts Practice Group. Ranked nationally himself in Government Contracts Law by Chambers, Law360, Benchmark Litigation, and Super Lawyers, Aron’s vast experience includes representation of government contractors in numerous industries…

Aron Beezley is the co-leader of Bradley’s nationally ranked Government Contracts Practice Group. Ranked nationally himself in Government Contracts Law by Chambers, Law360, Benchmark Litigation, and Super Lawyers, Aron’s vast experience includes representation of government contractors in numerous industries and in all aspects of the government-contracting process, including negotiation, award, performance and termination.

Read more about Aron C. BeezleyEmailAron's Linkedin Profile
Show more Show less
Photo of Nathaniel J. Greeson Nathaniel J. Greeson

Nathaniel Greeson helps clients solve government contracts challenges. Nathaniel represents clients in a range of government procurement issues, including bid protests, claims, disputes, audits and investigations. He has extensive experience with GAO bid protests, agency-level protests, Court of Federal Claims (COFC) bid protests…

Nathaniel Greeson helps clients solve government contracts challenges. Nathaniel represents clients in a range of government procurement issues, including bid protests, claims, disputes, audits and investigations. He has extensive experience with GAO bid protests, agency-level protests, Court of Federal Claims (COFC) bid protests, and SBA OHA size and NAICS appeals, as well as experience with agency-level requests for equitable adjustments (REA) and claims, and Boards of Contract Appeals claims. View articles by Nathaniel.

Read more about Nathaniel J. GreesonEmailNathaniel's Linkedin Profile
Show more Show less
Photo of Steven C. Herrera Steven C. Herrera

Steven Herrera is a senior attorney in the Construction and Government Contracts practice groups. His practice is primarily focused on U.S. government contracts and procurement law, particularly high-value procurements, billion-dollar litigation, and intricate bid protests.

Read more about Steven C. HerreraEmail
  • Posted in:
    Government Contracts
  • Blog:
    BuildSmart
  • Organization:
    Bradley Arant Boult Cummings LLP
  • Article: View Original Source

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
The Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo