The US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US Army Corps of Engineers’ environmental analysis likely violated the National Environmental Policy Act and the Clean Water Act due to the following deficiencies: The Corps did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by…
As we highlighted in our March 2, 2018, post, the US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US Army Corps of Engineers’ environmental analysis likely violated the National Environmental Policy Act (NEPA) and the Clean Water Act (CWA) due to the following deficiencies: The Corps did not provide sufficient explanation for how the…
A second district court has agreed that challenges to the 2015 Waters of the United States (WOTUS) Rule are likely to succeed on the merits. The US District Court for the Southern District of Georgia issued an order on June 8 enjoining the WOTUS Rule in 11 states. Georgia v. Pruitt, No. 2:15-cv-00079 (S.D. Ga. 2018). The rule was previously enjoined by the US District Court for North Dakota in 13 states. North Dakota v.…
On March 12, 2018, the United States Court of Appeals for the Second Circuit affirmed a Federal Energy Regulatory Commission (FERC) order finding that delays by the New York Department of Environmental Conservation (NYDEC) in reviewing Millennium Pipeline Company’s application for water quality certification constituted waiver of NYDEC’s authority under the Clean Water Act (CWA). Read the full report on PipelineLaw.com.…
On March 12, 2018, the United States Court of Appeals for the Second Circuit affirmed a Federal Energy Regulatory Commission (FERC) order finding that delays by the New York Department of Environmental Conservation (NYDEC) in reviewing Millennium Pipeline Company’s application for water quality certification constituted waiver of NYDEC’s authority under the Clean Water Act (CWA). As we detailed in an earlier blog post, FERC found that NYDEC’s delay exceeded the one-year statutory period established…
This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction, halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider…
This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction, halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider…
  On Monday, the Trump Administration released an ambitious legislative proposal that aims to stimulate $1.5 trillion in new infrastructure investment over the next 10 years, expedite the federal permitting process, address rural infrastructure needs, and prepare the American workforce for the future. To accomplish those goals, the proposal includes aggressive recommendations to streamline key federal environmental review and permitting processes for infrastructure projects. In addition to traditional forms of infrastructure, such as roads, bridges,…
Federal agencies that authorize or permit large infrastructure projects, like interstate natural gas pipelines, are often subject to the requirements of the National Environmental Policy Act (NEPA), and environmental organizations frequently rely on NEPA to challenge a project. The D.C. Circuit recently struck down a decision by the Federal Energy Regulatory Commission (FERC) to approve the construction and operation of three interstate natural gas pipelines because the Court found defects in FERC’s NEPA analysis. The…
Federal agencies that authorize or permit large infrastructure projects, like interstate natural gas pipelines, are often subject to the requirements of the National Environmental Policy Act (NEPA), and environmental organizations frequently rely on NEPA to challenge a project. The D.C. Circuit recently struck down a decision by the Federal Energy Regulatory Commission (FERC) to approve the construction and operation of three interstate natural gas pipelines because the Court found defects in FERC’s NEPA analysis. The…