U.S. District Court in Maryland Holds One-Year Statute of Limitations Under Miller Act Did Not Commence Until After Required Testing Performed by Subcontractor

By Jeffery R. Mullen
January 21, 2014

United States of America ex rel D&M General Contracting, Inc v. Arch Ins. Co.
2013 U.S. Dist. LEXIS 111260 (D. Md. Aug. 5, 2013)

This action arose out of subcontractor’s claim for increased costs allegedly incurred as a result of…

Call us at 1-800-913-0988 or email sales@lexblog.com.

Facebook LinkedIn Twitter RSS
Library at LexBlog
  • About LexBlog
  • The Field We Built
  • Library at LexBlog
  • Our Beliefs
  • Our Team
  • Contact LexBlog
  • Disclaimer
  • Editorial Policy
  • Terms of Service
  • Get Started
  • Publishing Solutions
  • Compass
  • Submit a Request
  • Support Center
  • System Status
Copyright © 2026, LexBlog, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo