“According to FERC, it is now commonplace for states to use Section 401 to hold federal licensing hostage.”
These are the words the DC Circuit used in Hoopa Valley Tribe v. Federal Energy Regulatory Commission, No. 14-1271, p. 10 (D.C.
PipelineLaw, published by Hunton Andrews Kurth LLP, focuses on legal developments and regulatory issues related to energy infrastructure, particularly pipelines. The blog covers topics such as federal eminent domain authority under the Natural Gas Act, state and federal regulatory enforcement actions, and the intersection of energy policy with environmental and climate change goals. It addresses litigation and administrative proceedings involving pipeline projects, including Supreme Court cases and Federal Energy Regulatory Commission (FERC) enforcement reports. The blog also discusses state-level investigations and policy shifts affecting natural gas distribution and energy transition strategies, providing insights into the evolving legal landscape for energy companies and regulators.
“According to FERC, it is now commonplace for states to use Section 401 to hold federal licensing hostage.”
These are the words the DC Circuit used in Hoopa Valley Tribe v. Federal Energy Regulatory Commission, No. 14-1271, p. 10 (D.C.
Last week, the US District Courts for the Eleventh and Sixth Circuits joined a growing chorus of other circuits holding that a Natural Gas Act (NGA) condemnor can obtain immediate, pre-trial possession of condemned land through a preliminary injunction (PI)…
In recent litigation involving the development of interstate natural gas pipelines, one of the key issues has been whether the state has waived its authority under Clean Water Act section 401 by exceeding the one-year time period. In a separate…
The issuance of FERC and PHMSA’s Memorandum of Understanding (MOU) last month potentially signals an improved review and authorization process for Liquefied Natural Gas (LNG) projects, but only time will tell how the MOU will work in practice and if…
The US Court of Appeals for the Third Circuit recently issued two decisions concerning the relationship between the Natural Gas Act (NGA) exclusive jurisdiction provision at 15 U.S.C. § 717r(d)(1) and the administrative review process for state-issued environmental permits for…
Earlier this month, the Pipeline and Hazardous Materials Safety Administration and the Federal Energy Regulatory Commission announced their intention to develop a memorandum of understanding (MOU) that would refine and reduce the permit application review process for proposed Liquefied Natural…
As we highlighted in our March 2, 2018, post, the US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US…