Skip to main content

Topic

Generator Interconnection

63 published works

  1. Washington Energy Report

    FERC Finalizes Generator Interconnection Procedures and Agreements Reforms

    By Meghan Mandel, Thomas DeVita

    On April 19, 2018, FERC issued a final rule ("Order No. 845") revising its pro forma Large Generator Interconnection Procedures (“LGIP”) and the pro forma Large Generator Interconnection Agreement (“LGIA”)…

  2. Washington Energy Report

    FERC Largely Denies Rehearing Request to Change Existing MISO Generator Interconnection Procedures

    By Meghan Mandel, Christopher Zentz

    On November 3, 2017, FERC largely denied rehearing requests from a group of generation developers (“Generation Developers”) regarding the Midcontinent Independent System Operator, Inc.’s (“MISO”) revisions to its Generator Interconnection…

  3. Washington Energy Report

    FERC Largely Denies Rehearing Request to Change Existing MISO Generator Interconnection Procedures

    By Meghan Mandel, Daniel Archuleta

    On November 3, 2017, FERC largely denied rehearing requests from a group of generation developers (“Generation Developers”) regarding the Midcontinent Independent System Operator, Inc.’s (“MISO”) revisions to its Generator Interconnection…

  4. Washington Energy Report

    FERC Conditionally Accepts MISO Interconnection Changes

    By Jamond Perry, Thomas DeVita

    On October 19, 2017, FERC accepted modifications to the Midcontinent Independent System Operator, Inc.’s (“MISO”) Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”), subject to certain conditions and…

  5. Washington Energy Report

    FERC Rejects Revisions to MISO’s Generator Interconnection Review Process Due to Lack of Justification

    By Meghan Mandel, Jasmine Hites

    On September 7, 2017, FERC rejected, without prejudice, Midcontinent Independent System Operator, Inc.’s ("MISO") proposed tariff revisions regarding its generator interconnection process.  FERC found that MISO did not provide sufficient…

  6. Inside Energy & Environment

    FERC IS BACK AND FACES A FULL PLATE OF ELECTRICITY ISSUES (Volume 2)

    By Bill Massey

    This is the second post of three on this blog providing short summaries of the generic electricity policy initiatives already teed up and awaiting possible action by the newly-constituted FERC. …

  7. Washington Energy Report

    FERC Accepts MISO’s Revisions to Generator Interconnection Procedures

    By Jasmine Hites

    On January 3, 2017, FERC accepted the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed revisions to its Generator Interconnection Procedures (“GIP”) and its pro forma Generator Interconnection Agreement (“GIA”) contained…

  8. Washington Energy Report

    FERC Proposes Generator Interconnection Changes

    By Thomas DeVita, Jasmine Hites

    On December 15, 2016, FERC issued a Notice of Proposed Rulemaking (“NOPR”) in which it proposed to revise its regulations and the pro forma Large Generator Interconnection Procedures (“LGIP”) and…

  9. Washington Energy Report

    FERC Upholds Applicability of CAISO Interconnection Procedures for Third-Parties Directly Interconnecting to WAPA-Owned Facilities

    By Adrienne Thompson, Christopher Zentz

    On November 4, 2016, FERC issued an order denying a complaint filed by HORUS Central Valley Solar 1, LLC and HORUS Central Valley Solar 2, LLC (jointly, “HORUS”) against the…

  10. Washington Energy Report

    FERC Declines to Require Removal of the Security Requirement for Transmission Owning Interconnection Customers under the MISO Pro Forma GIA

    By Adrienne Thompson, Jasmine Hites

    On September 9, 2016, FERC conditionally accepted an unexecuted Generator Interconnection Agreement (“GIA”) filed by the Midcontinent Independent System Operator, Inc. (“MISO” or the “ISO”) involving Duke Energy Indiana, LLC…