  1. Washington Energy Report

    FERC Amends the Pro Forma SGIA to Require Frequency and Voltage Ride-Through Capability for Small Generators

    By Adrienne Thompson, Daniel Archuleta

    On July 21, 2016, FERC issued a final rule (“Order No. 828”) modifying the pro forma Small Generator Interconnection Agreement (“SGIA”) to require newly interconnecting small generators to “ride-through” voltage…

  2. Energy & Environmental Law Adviser

    Small Generators May Soon Be Required to “Ride Through” System Disturbances

    By Nicole S. Allen

    The Federal Energy Regulatory Commission (FERC) has issued a Notice of Proposed Rulemaking (NOPR) to revise its pro forma Small Generator Interconnection Agreement (SGIA). The new rule would require small…

  3. Washington Energy Report

    FERC Issues NOPR Proposing Revisions to Pro Forma SGIA

    By Troutman Pepper

    On March 17, 2016, the Federal Energy Regulatory Commission (“FERC” or the “Commission”) issued a Notice of Proposed Rulemaking (“NOPR”) that would modify the pro forma Small Generator Interconnection Agreement…

  4. Washington Energy Report

    FERC Conditionally Approves Ten Categories of Revisions to CAISO Generator Interconnection Process

    By Troutman Pepper

    On March 7, 2016, the Federal Energy Regulatory Commission (“FERC” or the “Commission”) conditionally approved amendments to the California Independent System Operator Corporation’s (“CAISO”) Open Access Transmission Tariff (“OATT”) that…

  5. Washington Energy Report

    FERC Issues Order Closing Loophole in CAISO Generator Interconnection Process

    By Troutman Pepper

    On November 24, 2015, FERC issued an order accepting proposed CAISO tariff revisions, closing what has been described by CAISO as a loophole in CAISO’s generator interconnection process. CAISO proposed…

  6. Washington Energy Report

    FERC Denies Wind Generator Complaint Against MISO as Premature

    By Troutman Pepper

    On October 23, 2015, FERC issued an order denying a complaint brought by Merricourt Power Partners, LLC (“Merricourt”) – which has been developing a 150 MW wind farm in North…

  7. Washington Energy Report

    FERC Denies Rehearing and Grants Clarification of Order No. 807 Regarding Open Access and Priority Rights on Interconnection Customer’s Interconnection Facilities

    By Troutman Pepper

    On October 15, 2015, FERC issued an order denying rehearing and granting clarification of Order No. 807, which contained regulations and policies regarding open access to and priority rights on…

  8. Washington Energy Report

    AWEA Petitions FERC to Significantly Reform Pro Forma Generator Interconnection Procedures and Agreement

    By Troutman Pepper

    On July 7, 2015, the Commission issued a notice calling for comments on a Petition for Rulemaking filed by the American Wind Energy Association (“AWEA”) on June 19, 2015 in…

  9. Washington Energy Report

    FERC Institutes Section 206 Proceeding to Examine MISO Charges for Interconnection-Related Transmission Upgrades

    By Troutman Pepper

    On June 18, 2015, FERC issued an order granting in part and denying in part a complaint, and instituting a 206 proceeding to examine the justness and reasonableness of MISO’s…

  10. Environment, Land & Resources

    CAISO Energy Storage Interconnection Initiative

    By Latham & Watkins

    By Michael J. Gergen, Eli Hopson, and Andrew H. Meyer The California Independent System Operator (“CAISO”) is moving forward with a stakeholder initiative to examine issues with connecting energy storage facilities…